2012 Upper Section
The work continued
with building walls next to the fence, where the sentinel tower will go. We then
worked to the left before picking up at the end of the other section of walls. With
this area, the back of the wall is completely covered in the ice barrier as it will
have completely covering it, and the front only has it at the bottom where dirt
will be (the rest will be covered in pickets in the fall or next spring).
    
    
    
We then spent over a week digging out the huge hill left from where the
skid steer was moved in and out of the yard. It was really compacted clay! Mr. Man
had to get pick axes to use on it to break it up. The dirt was moved to areas where
we needed to raise the grade a bit. Oh yeah, we had a day or two of rain in there
also, which meant no working in the soupy, quick-sand Georgia Red Clay of the backyard.That
put us a week or so behind schedule as we couldn't work outside for a day and a half.
Plus the time it takes to move the dirt. Mr. Man breaks it up, the kids and I load the wagon,
then it's dumped out in the yard where ever it needs to go.
Now that the hill is removed, the big wall was built. That puppy is approx. 20 feet
long. We built it in pieces and put it up, just like all the other sections. While I
put the ice barrier on the wall, Mr. Man worked on tilling the trenches for the drainage
pipes. Then I took a turn with the tiller and killed it. Although the engine works,
the tines no longer turn. It was a pain to find a replacement (see the blog post
about that), but we found one, and Mr. Man continued tilling. It took through Monday to get
the main pipe area tilled, pipe in, and covered. It wouldn't have been such a problem except
we were supposed to get rain, so we wanted the pipe in. We made it, and the backyard is a little
soupy in a few spots where the ground is low, but it looks okay so far.
    
The area behind the big wall is my herb garden and small upper garden. For the first year, we've
planted tomatoes in it. The herbs here are chives, bay, sage, rosemary, thyme,
and savory. We'll see what does well and what needs to be adjusted. Alyx worked
really hard helping me put dirt behind the wall and adding the new soil so the
plants get the nutrients they need.
    
Since then, Mr. Man has been using the tiller to dig the trenches to put in the
drainage pipes so we don't have standing water in the playground area. It was really
tough work, even with the tiller because of how far down we had to go (15 inches in some
places). Then there was the whole fiasco where I broke the tiller. Yep, you read
that correctly. It appears the part the turns the tines has busted. So we lost over
a day, with rain looming in the forecast, trying to get a new one (whole other
adventure, read about in the blog). Fortunately, the second new one we got
worked, and Mr. Man was able to continue (that thing has a lot of power, and I
can do it for short bursts). While I was working with it one Monday afternoon,
I had to stop as I was putting a bend in the area we were going. Mr. Man took
a closer look at it when he got home, and the reason I couldn't go straight there
was because of a HUGE tree stump. He spent the next hour trying to bust it up- using the pick
axe, reciprocating saw, and whatever else he could (and broke the little pick axe in the
process). Regardelss, he was able to finish the long section of pipe, and the kids
and I buried it, before the rains came. He then put the short side shoot in, which
took a bit of time as he had to stop Monday because it was too dry (so we watered it),
then the rains came, and he was only able to go a few inches down before it was
so wet it gunked up the tiller. Another 24 hours later, he was able to finish.
So now we are back on wall building (Grandpa B. and I picked it up Friday), which
means the end is almost in sight for this part of the project. Still much to go,
but it's moving forward.
The last wall segments were built, and then we started grading. Unfortunately,
we ran into weather delays (over multiple weeks) that slowed us down. We tried to make
use of the time by starting pool destruction (see the backyard page for those photos).
    
We finished grading this area by the middle of May:
    
While Grandma and Grandpa B. were here Memorial Day to help with the pool base, the holes were marked and dug
out (by hand and with the gas-powered, rented, post hole digger. Plus, a pole was put in:
    
We'll get the holes cleaned out and the posts put in over the next few days (hopefully before the rain comes!).
As the summer continued, we got posts in and used a lot of concrete. I think I made
4 or 5 trips to the orange home improvement store to get 8-10 bags each time, plus loaded
it into my car, half the time without their "help". By the way, the male cashiers don't
like it when one points that out to them and will come help load when their "staff" has
disappeared. Once all but the tire swing post were in and secured, we moved down
to the pool base and got that functioning.
    
After that, it was back up top to the playground. Supports were put in, and posts have been extended. By early August,
the kids had a sand box (unexpected addition to the plan), swings, and tire swing. We also got the first
layer of wood chips spread out. Progress in July had been slow due to rain, and rain,
and oh yeah, there was that rain that came, which lead to upstairs being unworkable
until the wood chips were added, even days after the rain stopped. Next up is to finish
some posts to start to give it more structure before adding joists and bottom layers.
Check out the next steps here.